Benidorm's prized high-rise tower becomes a symbol of incompetence
"Bad bank" Sareb holds InTempo's financing as architects resign in frustration
In May 2012, when Benidorm government officials climbed up the InTempo - the European Union's tallest residential building still under construction - for a photo op, they had an idea. The twin towers joined at the top by a cone were to become a symbol of the post-crisis takeoff of the Spanish city of skyscrapers par excellence. (Once a fishing village, Benidorm is now famous - or infamous, depending on the viewpoint - for a glut of high-rises that have earned it the nickname "Beniyork.")
But in late December, with 94 percent of the building completed and 35 percent of units sold, Spain's bad bank, Sareb, announced that it was taking on the loan that a savings bank had extended to the developer eight years ago.
EL PAÍS has had access to documents showing that the building that was meant to represent a glorious turning point in the history of Benidorm, but in fact it represents a long story of incompetence.
Its beginnings date back to a joyous time of unlimited credit and unfettered development. A construction firm, Olga Urbana, pompously advertised what was going to be "an unquestionable banner of the future." The landmark building would rise meters up into the clouds. The now-defunct Caixa Galicia extended a 92-million euro loan in 2005 - a mortgage that ended up at Nova Caixa Galicia following the merger of Galician savings banks. Now Sareb has assumed the loan for 46 million euros, representing a debt release of 50 percent.
It dates back to a time of unlimited credit and unfettered development
The inauguration was initially scheduled for mid-2009, then pushed back to the summer of 2011. For months, it was evident that no progress was being made at all on the site. But the project's real situation did not emerge until last week, and it is a complex one: although the loan belongs to Sareb, the contract shows that building itself is the property of Olga Urbana, and only a realtor called Maxxima may sell it.
In fact, the unfinished story of this urban behemoth of 47 floors and 269 housing units is one long compilation of atypical situations. Sources familiar with the project said that the first sign of trouble came in 2009 when the builder went bankrupt. The crisis was roaring by then, and the savings bank stopped construction work and conducted a viability study. The lender then hired a Madrid firm, Suasor, to handle the project's expenses. Any money saved would be a commission for Suasor.
Workers from the defunct construction firm created a new one, Kono, and drafted a proposal for the building's completion. Suasor seemed initially quite keen, but ultimately gave the project to another Madrid firm, Eyte. Eyte's proposal shows an uncanny resemblance to the one present by Kono. The only difference is that the Madrid study contained serious mistakes. In one instance, it miscalculated the position of the steel structure by seven floors, and in another flaw, it offered outdated prices for the 2,500 tons of steel required. Olga Urbana made the final decision: the former building workers would get the project back. But the relationship between Kono and Suasor from then on was anything but smooth.
And so in 2010, work resumed in fits and starts. After the first month, Caixa Galicia put payments on hold because it wanted all workers to open up an account and deposit their monthly wages with the lender. But the builder refused. Later, workers went four months without pay. It is also worth mentioning that until the first 23 floors were built, it did not occur to managers to set up a freight elevator for the 41 workers who kept having to trek up and down the stairs.
For months, it was evident no progress was being made at all on the site
But there's more. In April 2011, when the concrete already reached the 46th floor, the floor plans for the 47th story were not ready yet. In July, the freight elevator collapsed with 13 workers inside and the ambulances were unable to access the site because no vehicle entrance had been built in order to save money. Several workers were seriously injured.
In August, workers threatened to go on strike after all the late payments. The e-mail reply from Javier Frías, a manager, was: "There could be some people who may not be interested in the working conditions and decide to walk away. They'll be doing us a favor."
In January 2012, there was a new surprise: the elevator shaft had not been taken into account, as the promotional designs clearly show. "The space was calculated for a 20-storey building," said the same sources. Then, in May, the architects directing the project resigned. They have declined to comment on the case.
InTempo is about 94 percent complete, with 35 percent of the apartments sold. The new completion date is December 2013, but the project is being held back by fraud complaints, embargoes and other claims by clients and providers. Unfazed, developers have not brought down prices: a one-bedroom apartment has a price tag of 358,000 euros, with increments every 10 floors.
The building meant to symbolize an era is just that - a symbol for an era of excess.
Tu suscripción se está usando en otro dispositivo
¿Quieres añadir otro usuario a tu suscripción?
Si continúas leyendo en este dispositivo, no se podrá leer en el otro.
FlechaTu suscripción se está usando en otro dispositivo y solo puedes acceder a EL PAÍS desde un dispositivo a la vez.
Si quieres compartir tu cuenta, cambia tu suscripción a la modalidad Premium, así podrás añadir otro usuario. Cada uno accederá con su propia cuenta de email, lo que os permitirá personalizar vuestra experiencia en EL PAÍS.
En el caso de no saber quién está usando tu cuenta, te recomendamos cambiar tu contraseña aquí.
Si decides continuar compartiendo tu cuenta, este mensaje se mostrará en tu dispositivo y en el de la otra persona que está usando tu cuenta de forma indefinida, afectando a tu experiencia de lectura. Puedes consultar aquí los términos y condiciones de la suscripción digital.